TOWN PLANNING:
Tommy Brümmer https://www.tommybrummer.co.za/
The GR2 (General Residential two) zoning is favourable, consolidation of all erwen in a row, would drop any title deed restrictions and needs to be applied for which we can proceed with once all four erwen are owned by the same owner.
This process alone could take anywhere from 12 up to 18 eighteen months, worst case scenario 24 months, as the public would be required to participate in this departure approval.
Planning approval will take around six months. So it could be up to 2.5 years before construction can begin.
However, we have identified a more suitable alternative which is more favourable in this regard, and that is to undergo a notarial tie of all four erven once they have been acquired and to apply for the relevant departures of removing restrictions on title deeds and other issues.